• Offshore Platform Construction: Topside Module Installation

    On an offshore oil platform, topsides (c.f. jacket structure, which constitutes the lower half of the platform structure, partly submerged in sea) refers to the upper half of the structure, above the sea level, outside the splash zone, on which equipment is installed. This includes the oil production plant, the accommodation block and the drilling rig. They are often modular in design and so can be changed out if necessary allowing expensive platforms to be more readily updated with newer technology. Thanks to http://ccmixter.org/files/SackJo22/43036 for awesome audio.

    published: 17 Aug 2013
  • Wheatstone Project Completes Topsides Float-Over Installation

    The Wheatstone Project successfully completed one of the largest offshore platform installations in Chevron's history, marking a major project milestone. Watch the journey of the Wheatstone topsides from fabrication to load-out, the sail-away, the arrival and the float-over onto the steel-gravity structure base. The Wheatstone Platform is the largest offshore gas processing platform ever installed in Australia, with a topsides weight of about 37,000 metric tons and the largest float-over installation Chevron has ever delivered globally. To learn more about the Wheatstone project visit http://www.chevron.com/countries/australia/businessportfolio/projectprogress/ To learn more about Chevron visit http://www.chevron.com

    published: 01 May 2015
  • Offshore Platform Installation- Jacket Installation and Topside Installation

    http://www.oceanicmc.com/ Oceanic 5000 is a DP2 Derrick Lay Vessel which can install offshore structures including jackets and topsides weighing up to 4400MT. The state-of-the-art Oceanic 5000 can also lay subsea pipelines utilizing her two double-joint stations resulting in considerable increase in lay rates. This video demonstrates installation of a 2000t jacket by launching method and a 1500t topside (deck) by lifting method. The entire pipe lay assembly process is carried out below the main working deck. This allows maximum pipe storage above deck and more free deck space for structural installation; thereby providing a safer and more productive working condition. The vessel is equipped with a specially-designed “piggy-back” system for the installation of carrier pipes to be simulta...

    published: 19 Aug 2014
  • Clair Ridge - topsides installation

    16,000 combined tonnes of weight. 3 modules. 75km out to sea. Watch this incredible ‪‎timelapse‬ of the topsides being installed on our Clair Ridge platform, offshore UK

    published: 21 Jul 2015
  • Pioneering Spirit removing the Yme topsides HD

    Allseas giant platform removal and installation vessel removed the 13,500-tonne topsides of the Yme platform on 22 August 2016

    published: 05 Oct 2016
  • Pioneering Spirit removing the Brent Delta topsides HD

    Allseas' "Pioneering Spirit" removes the 24,000 Tons Brent D Topsides for Shell UK in the North Sea on 28 April 2017

    published: 31 May 2017
  • Super Rig: Troll "A" Gas Platform

    The Troll A platform is a condeep offshore natural gas platform in the Troll gas field off the west coast of Norway. It is the tallest structure that has ever been moved to another position, relative to the surface of the Earth, and is among the largest and most complex engineering projects in history. The platform was a televised sensation when it was towed into the North Sea in 1996, where it is now operated by Statoil. Troll A was built by Norwegian Contractors for Norske Shell, with base construction beginning in July 1991 at a cost of 4150 million NOK, or approximately US$650,000,000 at the time. The base and the deck were built separately, and were joined in 1995 while the base was partially submerged. The base is a Condeep gravity base structure built from reinforced concrete. The...

    published: 07 Jan 2015
  • Edvard Grieg topside lift operation

    Lundin Norway has successfully completed the installation of the topside modules on the Edvard Grieg field, offshore Norway. The Edvard Grieg topside installation consisted of lifting four modules onto the pre-installed jacket – the main deck frame, the utility and living quarters module, the processing module and the flare boom with a total weight of 22,000 tonnes. The lift operation was carried out by Heerema’s heavy lift vessel Thialf.

    published: 28 Jul 2015
  • Topsides

    Hebron topsides

    published: 06 Aug 2016
  • Mammoet - Mega load out of BP Clair Topside

    Loading one of the heaviest topsides ever onto a deck barge for offshore installation. See how 14000 ton is driven onto a barge while going through changing water levels

    published: 18 Oct 2014
  • Heavy lifting on Mariner!

    The Mariner A topside is now complete! On 2 August the final piece of the giant puzzle was lifted into place on the 38 000 tonne topside. The topside consists of eight modules, two of them more than 10 000 tonnes. The flare, a crane and some stair towers have also been installed offshore by heavy lift vessel Saipem 7000. Now the floatel Safe Boreas is connected to the platform and the two million man hour topside scope can begin. The Mariner field is expected to come on stream late 2018.

    published: 07 Aug 2017
  • Hebron

    Topsides

    published: 30 Sep 2016
  • Installing the Biggest Oil and Gas Platform in the Caspian Sea

    19,000 tonnes of jacket, 7,000 tonnes of piles and 20,000 tonnes of topsides. All completed in 2013. Unofficial video by a budding installation engineer; professional video also available on youtube. West Chirag PDQ Operator: BP (on behalf of AIOC) Installation contractor: Saipem Music by Deadmau5

    published: 24 Sep 2013
  • Offshore accident while building a platform

    Offshore accident / Gintung Jacket. When building a platform, something goes wrong and the whole platform disappears into the ocean

    published: 02 Sep 2010
  • Heera HRD topside transport & float-over

    Load-out, transport and float-over installation of the HEERA HRD gas platform. The Dockwise vessel Fjell transported the topside of the Heera HRD gas platform from Vietnam to India.

    published: 05 Nov 2015
  • Offshore Platform Construction: Topside Module Installation

    HeavyEquipmentAccidents #RC #Agriculture #2017 Allseas giant platform removal and installation vessel removed the 13500-tonne topsides of the Yme . Этот ролик обработан в Видеоредакторе YouTube ( HeavyEquipmentAccidents #RC #Agriculture #2017 tree trimming equipment - tree clearing machine - skid steer brush cutter. tree clearing machine - skid steer .

    published: 05 Dec 2017
  • Shallow water Platforms Project--Topside Deck Installation at T-REX Fabrication Facility, Houston TX

    published: 04 Sep 2013
  • The 5 Largest Offshore Platforms of the World

    Offshore platforms are remarkable engineering feats, therefor it is time for the 5 largest offshore platforms of the world! Massive in size, these structures take several years and often many billions of dollars to build — but when complete, they can extract oil and gas from some of the least-accessible spots on the planet. The Mars B/Olympus Platform in the Gulf of Mexico First oil production begun in February 2014 from the Mars B development through Olympus, Shell’s seventh, and largest, floating deep-water platform in the Gulf of Mexico. Combined production from Olympus and Shell’s original Mars platform is expected to deliver an estimated resource base of 1 billion barrels of oil equivalent (boe). The project is also directly investing $5 million dollars in community, social and env...

    published: 11 May 2017
  • 24,000 tonne platform topside arrives in Norway

    The 24 000 tonne topside for the Aasta Hansteen gas platform arrived in Norway on 30 November after a 14 500 nautical mile long journey. That’s equivalent to nearly 26 900 km, or more than 640 marathons! The lady was brought home to Norway by Dockwise White Marlin. In Ølensvåg the topside will be transferred to two new vessels that will take it to Stord to be mated with the substructure, creating the world’s largest spar-platform.

    published: 01 Dec 2017
  • Stampede Milestone: Topsides Lift

    The topsides lift was executed safely and successfully at Ingleside, TX earlier this year.

    published: 15 Dec 2016
  • Iranian $40 Million Oil Platform sinks to bottom of Persian Gulf

    A $40-million (U.S.) engineering structure belonging to Iran's South Pars gas field to be used in offshore platforms sank into the Gulf as it was being installed, media reports said on Wednesday. "An investigation is under way," Maritime Industrial Co. (SADRA) managing director Mehdi Etesami told the ISNA news agency, without giving an official reason for the incident.Iran later called for foreign help to recover the gas platform from the seabed, its Mehr news agency reported, in a rare request by an industry isolated by sanctions. The equipment was built by SADRA, an affiliate of the industrial wing of Iran's Revolutionary Guards, over a 30-month period. The incident occurred Monday night as the 1,850-tonne jacket developed for South Pars Phase 13 sank to a depth of 80 metres, media re...

    published: 04 Feb 2013
  • Allseas Pioneering Spirit removing Brent Delta topsides 1080p

    Allseas' "Pioneering Spirit" removes the 24,000 Tons Brent D Topsides for Shell UK in the North Sea

    published: 29 Apr 2017
  • Gina Krog topside installation August 2016

    In less than a week all the modules for the Gina Krog topside was installed at the field in the North Sea in August 2016 by Saipem 7000. The complete weight of the topside is close to 20 000 tonne. The main support frame, process module and utility module was constructed by DSME at Okpo, South Korea, the living quarter was constructed by Apply Leirvik at Stord, Norway. The Gina Krog platform will come on stream in 2017.

    published: 28 Aug 2016
  • Anadarko: Lucius Topsides Installation

    Hundreds of people worked around the clock to successfully install the 10,000-ton topsides on Anadarko's floating Lucius truss spar. This massive structure is located nearly 275 miles southeast of Galveston, Texas in approximately 5,300 feet of water in the Gulf of Mexico. The successful setting of the topsides brought together a tapestry of components built in Orange, Texas; Houma, La; and Ingleside, Texas, among other locations worldwide. Lucius is Anadarko's largest spar to date with a nameplate capacity of 80,000 barrels of oil per day.

    published: 10 Jun 2014
  • Offshore Platform Construction Topside Module Installation

    Offshore Platform Construction Topside Module Installation

    published: 13 Jul 2017
  • Offshore Platform Construction Topside Module Installation

    published: 12 May 2017
  • Single Lift Vessel Platform Removal

    SLCV demonstration movie showing the removal of a platform topsides in a single lift.

    published: 14 Aug 2017
  • Offshore Platform Construction Topside Module Installation

    published: 28 Aug 2014
  • Offshore Platform Construction- Topside Module Installation HOT MOBILE LOCATION

    published: 14 May 2017
developed with YouTube
Offshore Platform Construction: Topside Module Installation

Offshore Platform Construction: Topside Module Installation

  • Order:
  • Duration: 5:31
  • Updated: 17 Aug 2013
  • views: 157891
videos
On an offshore oil platform, topsides (c.f. jacket structure, which constitutes the lower half of the platform structure, partly submerged in sea) refers to the upper half of the structure, above the sea level, outside the splash zone, on which equipment is installed. This includes the oil production plant, the accommodation block and the drilling rig. They are often modular in design and so can be changed out if necessary allowing expensive platforms to be more readily updated with newer technology. Thanks to http://ccmixter.org/files/SackJo22/43036 for awesome audio.
https://wn.com/Offshore_Platform_Construction_Topside_Module_Installation
Wheatstone Project Completes Topsides Float-Over Installation

Wheatstone Project Completes Topsides Float-Over Installation

  • Order:
  • Duration: 2:20
  • Updated: 01 May 2015
  • views: 29745
videos
The Wheatstone Project successfully completed one of the largest offshore platform installations in Chevron's history, marking a major project milestone. Watch the journey of the Wheatstone topsides from fabrication to load-out, the sail-away, the arrival and the float-over onto the steel-gravity structure base. The Wheatstone Platform is the largest offshore gas processing platform ever installed in Australia, with a topsides weight of about 37,000 metric tons and the largest float-over installation Chevron has ever delivered globally. To learn more about the Wheatstone project visit http://www.chevron.com/countries/australia/businessportfolio/projectprogress/ To learn more about Chevron visit http://www.chevron.com
https://wn.com/Wheatstone_Project_Completes_Topsides_Float_Over_Installation
Offshore Platform Installation- Jacket Installation and Topside Installation

Offshore Platform Installation- Jacket Installation and Topside Installation

  • Order:
  • Duration: 3:33
  • Updated: 19 Aug 2014
  • views: 185893
videos
http://www.oceanicmc.com/ Oceanic 5000 is a DP2 Derrick Lay Vessel which can install offshore structures including jackets and topsides weighing up to 4400MT. The state-of-the-art Oceanic 5000 can also lay subsea pipelines utilizing her two double-joint stations resulting in considerable increase in lay rates. This video demonstrates installation of a 2000t jacket by launching method and a 1500t topside (deck) by lifting method. The entire pipe lay assembly process is carried out below the main working deck. This allows maximum pipe storage above deck and more free deck space for structural installation; thereby providing a safer and more productive working condition. The vessel is equipped with a specially-designed “piggy-back” system for the installation of carrier pipes to be simultaneously attached to the main trunk line during the lay operation. The stinger is 74 meters long connected by a hinged A-frame to the stern. The vessel is equipped with three 80T tensioners. The crane is designed to address the majority of lifting requirements including heavy lift installations, near shore lifting, and platform removal. The lift capacities of the main block (4400mt at 37 meters) and the auxiliary block (800mt at 35 meters) enable the vessel to undertake an impressive range of projects. Moreover, the 3000T fully-revolving condition increases efficiency, workability and control of heavy lift operations. Oceanic 5000′s relatively shallow draft provides access to work in shallow waters and fabrication yards. This versatility, combined with the ability to utilize both anchor and DP2 positioning systems, enable OMC the flexibility to perform the entire scope of work irrespective of water depths. The vessel propulsion system, designed to transit at 12 knots, allows her to reach locations in a swift and cost-effective manner.
https://wn.com/Offshore_Platform_Installation_Jacket_Installation_And_Topside_Installation
Clair Ridge - topsides installation

Clair Ridge - topsides installation

  • Order:
  • Duration: 3:07
  • Updated: 21 Jul 2015
  • views: 24249
videos
16,000 combined tonnes of weight. 3 modules. 75km out to sea. Watch this incredible ‪‎timelapse‬ of the topsides being installed on our Clair Ridge platform, offshore UK
https://wn.com/Clair_Ridge_Topsides_Installation
Pioneering Spirit removing the Yme topsides HD

Pioneering Spirit removing the Yme topsides HD

  • Order:
  • Duration: 10:52
  • Updated: 05 Oct 2016
  • views: 182554
videos
Allseas giant platform removal and installation vessel removed the 13,500-tonne topsides of the Yme platform on 22 August 2016
https://wn.com/Pioneering_Spirit_Removing_The_Yme_Topsides_Hd
Pioneering Spirit removing the Brent Delta topsides HD

Pioneering Spirit removing the Brent Delta topsides HD

  • Order:
  • Duration: 7:48
  • Updated: 31 May 2017
  • views: 45489
videos
Allseas' "Pioneering Spirit" removes the 24,000 Tons Brent D Topsides for Shell UK in the North Sea on 28 April 2017
https://wn.com/Pioneering_Spirit_Removing_The_Brent_Delta_Topsides_Hd
Super Rig: Troll "A" Gas Platform

Super Rig: Troll "A" Gas Platform

  • Order:
  • Duration: 50:04
  • Updated: 07 Jan 2015
  • views: 1306387
videos
The Troll A platform is a condeep offshore natural gas platform in the Troll gas field off the west coast of Norway. It is the tallest structure that has ever been moved to another position, relative to the surface of the Earth, and is among the largest and most complex engineering projects in history. The platform was a televised sensation when it was towed into the North Sea in 1996, where it is now operated by Statoil. Troll A was built by Norwegian Contractors for Norske Shell, with base construction beginning in July 1991 at a cost of 4150 million NOK, or approximately US$650,000,000 at the time. The base and the deck were built separately, and were joined in 1995 while the base was partially submerged. The base is a Condeep gravity base structure built from reinforced concrete. The Troll platform was towed over 200 kilometres (120 mi) from Vats, in the northern part of Rogaland, to the Troll field, 80 kilometres (50 mi) north-west of Bergen. The tow took seven days.
https://wn.com/Super_Rig_Troll_A_Gas_Platform
Edvard Grieg topside lift operation

Edvard Grieg topside lift operation

  • Order:
  • Duration: 4:02
  • Updated: 28 Jul 2015
  • views: 22866
videos
Lundin Norway has successfully completed the installation of the topside modules on the Edvard Grieg field, offshore Norway. The Edvard Grieg topside installation consisted of lifting four modules onto the pre-installed jacket – the main deck frame, the utility and living quarters module, the processing module and the flare boom with a total weight of 22,000 tonnes. The lift operation was carried out by Heerema’s heavy lift vessel Thialf.
https://wn.com/Edvard_Grieg_Topside_Lift_Operation
Topsides

Topsides

  • Order:
  • Duration: 1:37
  • Updated: 06 Aug 2016
  • views: 227
videos
Hebron topsides
https://wn.com/Topsides
Mammoet - Mega load out of BP Clair Topside

Mammoet - Mega load out of BP Clair Topside

  • Order:
  • Duration: 8:15
  • Updated: 18 Oct 2014
  • views: 137499
videos
Loading one of the heaviest topsides ever onto a deck barge for offshore installation. See how 14000 ton is driven onto a barge while going through changing water levels
https://wn.com/Mammoet_Mega_Load_Out_Of_Bp_Clair_Topside
Heavy lifting on Mariner!

Heavy lifting on Mariner!

  • Order:
  • Duration: 6:50
  • Updated: 07 Aug 2017
  • views: 18325
videos
The Mariner A topside is now complete! On 2 August the final piece of the giant puzzle was lifted into place on the 38 000 tonne topside. The topside consists of eight modules, two of them more than 10 000 tonnes. The flare, a crane and some stair towers have also been installed offshore by heavy lift vessel Saipem 7000. Now the floatel Safe Boreas is connected to the platform and the two million man hour topside scope can begin. The Mariner field is expected to come on stream late 2018.
https://wn.com/Heavy_Lifting_On_Mariner
Hebron

Hebron

  • Order:
  • Duration: 1:27
  • Updated: 30 Sep 2016
  • views: 1643
videos
Topsides
https://wn.com/Hebron
Installing the Biggest Oil and Gas Platform in the Caspian Sea

Installing the Biggest Oil and Gas Platform in the Caspian Sea

  • Order:
  • Duration: 3:42
  • Updated: 24 Sep 2013
  • views: 25416
videos
19,000 tonnes of jacket, 7,000 tonnes of piles and 20,000 tonnes of topsides. All completed in 2013. Unofficial video by a budding installation engineer; professional video also available on youtube. West Chirag PDQ Operator: BP (on behalf of AIOC) Installation contractor: Saipem Music by Deadmau5
https://wn.com/Installing_The_Biggest_Oil_And_Gas_Platform_In_The_Caspian_Sea
Offshore accident while building a platform

Offshore accident while building a platform

  • Order:
  • Duration: 1:42
  • Updated: 02 Sep 2010
  • views: 226133
videos
Offshore accident / Gintung Jacket. When building a platform, something goes wrong and the whole platform disappears into the ocean
https://wn.com/Offshore_Accident_While_Building_A_Platform
Heera HRD topside transport & float-over

Heera HRD topside transport & float-over

  • Order:
  • Duration: 1:51
  • Updated: 05 Nov 2015
  • views: 4350
videos
Load-out, transport and float-over installation of the HEERA HRD gas platform. The Dockwise vessel Fjell transported the topside of the Heera HRD gas platform from Vietnam to India.
https://wn.com/Heera_Hrd_Topside_Transport_Float_Over
Offshore Platform Construction: Topside Module Installation

Offshore Platform Construction: Topside Module Installation

  • Order:
  • Duration: 25:10
  • Updated: 05 Dec 2017
  • views: 5
videos
HeavyEquipmentAccidents #RC #Agriculture #2017 Allseas giant platform removal and installation vessel removed the 13500-tonne topsides of the Yme . Этот ролик обработан в Видеоредакторе YouTube ( HeavyEquipmentAccidents #RC #Agriculture #2017 tree trimming equipment - tree clearing machine - skid steer brush cutter. tree clearing machine - skid steer .
https://wn.com/Offshore_Platform_Construction_Topside_Module_Installation
Shallow water Platforms Project--Topside Deck Installation at T-REX Fabrication Facility, Houston TX

Shallow water Platforms Project--Topside Deck Installation at T-REX Fabrication Facility, Houston TX

  • Order:
  • Duration: 4:58
  • Updated: 04 Sep 2013
  • views: 1136
videos
https://wn.com/Shallow_Water_Platforms_Project_Topside_Deck_Installation_At_T_Rex_Fabrication_Facility,_Houston_Tx
The 5 Largest Offshore Platforms of the World

The 5 Largest Offshore Platforms of the World

  • Order:
  • Duration: 3:20
  • Updated: 11 May 2017
  • views: 7992
videos
Offshore platforms are remarkable engineering feats, therefor it is time for the 5 largest offshore platforms of the world! Massive in size, these structures take several years and often many billions of dollars to build — but when complete, they can extract oil and gas from some of the least-accessible spots on the planet. The Mars B/Olympus Platform in the Gulf of Mexico First oil production begun in February 2014 from the Mars B development through Olympus, Shell’s seventh, and largest, floating deep-water platform in the Gulf of Mexico. Combined production from Olympus and Shell’s original Mars platform is expected to deliver an estimated resource base of 1 billion barrels of oil equivalent (boe). The project is also directly investing $5 million dollars in community, social and environmental initiatives with the aim to benefit the communities of the US Gulf Coast, as well as in South Korea, where the hull of the Olympus platform was built. Olympus sailing into the Gulf of Mexico Olympus sailing into the Gulf of Mexico The Hibernia Platform in the Canadian Atlantic Hibernia is an oil field in the North Atlantic Ocean, approximately 315 kilometres (196 mi) east-southeast of St. John’s, Newfoundland, Canada, in 80 m of water. The production platform Hibernia is the world’s largest oil platform (by weight) and consists of a 37,000 t (41,000 short tons) integrated topsides facility mounted on a 600,000 t (660,000 short tons) gravity base structure. The platform was towed to its final site, and 450,000 t (500,000 short tons) of solid ballast were added to secure it in place. Inside the gravity base structure are storage tanks for 1.2 million barrels (190,000 m3) of crude oil. The Hibernia Platform in the Canadian Atlantic The Hibernia Platform in the Canadian Atlantic The Petronius Platform in the Gulf of Mexico Petronius is a deepwater compliant tower oil platform operated by Chevron Corporation and Marathon Oil in the Gulf of Mexico, 210 km southeast of New Orleans, United States. A compliant piled tower design, it is 609.9 metres (2,001 ft) high, and was arguably the tallest free-standing structure in the world, until surpassed by the Burj Khalifa in 2010, although this claim is disputed since only 75 metres of the platform are above water. The multi-deck topsides are 64 metres by 43 metres by 18.3 metres high and hold 21 well slots, and the entire structure weighs around 43,000 tons. Around 8,000 m3 (50,000 barrels) of oil and 2,000,000 m3 (70 million cubic feet) of natural gas are extracted daily by the platform. The jacket supports topsides weighing 7,500t. The jacket supports topsides weighing 7,500t. The Perdido Platform in the Gulf of Mexico Perdido is the world’s deepest spar, and the second-deepest oil and gas production hub after Shell’s Stones development. Moored in around 2,450 metres (8,000 feet) of water in the US Gulf of Mexico, Perdido started production in 2010, opening up a new frontier in deep-water oil and gas recovery. The Perdido Platform in the Gulf of Mexico The Perdido Platform in the Gulf of Mexico The Berkut Platform in the Sea of Okhotsk on the Russian Pacific Coast Russia’s Rosneft and Americas ExxonMobil have launched a unique drilling platform in the Okhotsk Sea in Russia’s Far East. The world’s most powerful rig can drill within the radius of at least 7 kilometers. The drilling platform can withstand a 9 magnitude earthquake, waves of up to 18 meters and temperatures down to minus 44 degrees Celsius, Rosneft President Igor Sechin said. Berkut can also withstand floating ice up to two meters thick and has an autonomous power supply system. It has the largest superstructure on any rig. Weighing 200,000 tons it can drill a total of 45 wells. The platform is located 25 km offshore in waters up 35 meters deep. The drilling will be performed by means of a marine rig, which allows all-year-round drilling of wells. http://ttalents.com/5-largest-offshore-platforms/
https://wn.com/The_5_Largest_Offshore_Platforms_Of_The_World
24,000 tonne platform topside arrives in Norway

24,000 tonne platform topside arrives in Norway

  • Order:
  • Duration: 1:27
  • Updated: 01 Dec 2017
  • views: 3906
videos
The 24 000 tonne topside for the Aasta Hansteen gas platform arrived in Norway on 30 November after a 14 500 nautical mile long journey. That’s equivalent to nearly 26 900 km, or more than 640 marathons! The lady was brought home to Norway by Dockwise White Marlin. In Ølensvåg the topside will be transferred to two new vessels that will take it to Stord to be mated with the substructure, creating the world’s largest spar-platform.
https://wn.com/24,000_Tonne_Platform_Topside_Arrives_In_Norway
Stampede Milestone: Topsides Lift

Stampede Milestone: Topsides Lift

  • Order:
  • Duration: 0:50
  • Updated: 15 Dec 2016
  • views: 940
videos
The topsides lift was executed safely and successfully at Ingleside, TX earlier this year.
https://wn.com/Stampede_Milestone_Topsides_Lift
Iranian $40 Million Oil Platform sinks to bottom of Persian Gulf

Iranian $40 Million Oil Platform sinks to bottom of Persian Gulf

  • Order:
  • Duration: 0:37
  • Updated: 04 Feb 2013
  • views: 155533
videos
A $40-million (U.S.) engineering structure belonging to Iran's South Pars gas field to be used in offshore platforms sank into the Gulf as it was being installed, media reports said on Wednesday. "An investigation is under way," Maritime Industrial Co. (SADRA) managing director Mehdi Etesami told the ISNA news agency, without giving an official reason for the incident.Iran later called for foreign help to recover the gas platform from the seabed, its Mehr news agency reported, in a rare request by an industry isolated by sanctions. The equipment was built by SADRA, an affiliate of the industrial wing of Iran's Revolutionary Guards, over a 30-month period. The incident occurred Monday night as the 1,850-tonne jacket developed for South Pars Phase 13 sank to a depth of 80 metres, media reports said, adding that there were no reports of casualties. Because of its links to the Guards, SADRA is subject to sanctions imposed by the European Union and the United States over Tehran's controversial nuclear program. Along with other industrial subsidiaries of Guards engineering wing the Khatam al-Anbiya group, SADRA was in 2010 awarded a $5-billion contract to develop Phase 13 after Western energy majors withdrew over the sanctions. Tehran considers the development of the South Pars field, which is jointly owned by Qatar, to be a strategic priority. Iran says it currently produces about 650 million cubic metres of gas daily, including 280 million from South Pars, most of which is used for domestic consumption. President Mahmoud Ahmadinejad said in early January that Iran plans to double the field's production capacity by summer 2013, but the accident is expected to delay the launch of Phase 13 by several months. Once completed, Phase 13 is to produce around 56 million cubic metres of gas daily. Major Western companies that previously operated in South Pars, among them France's Total SA and Anglo-Dutch giant Royal Dutch Shell PLC, withdrew from Iran between 2007 and 2010 after sanctions were imposed over Tehran's atomic ambitions. Iran, which has the world's second-largest natural gas reserves after Russia, claims it is able to develop South Pars on its own by giving many of the projects to companies affiliated to the Guards. لنفط الايراني منصة 40 مليون دولار لأسفل المصارف الخليج الفارسي Ιρανική 40 εκατομμύρια δολάρια νεροχύτες πλατφόρμα πετρελαίου προς τα κάτω του Περσικού Κόλπου Iraniane 40 milioni di dollari del petrolio affonda piattaforma verso il basso del Golfo Persico ペルシャ湾の底にイランの40百万ドルの石油プラットフォームのシンク 페르시아 만 (Persian Gulf)의 하단으로이란 4,000 만 달러 석유 플랫폼 싱크 Iranianas $ 40 milhões de petróleo afunda plataforma para fundo do Golfo Pérsico Иранские $ 40 млн. нефтяной платформы опускается на дно Персидского залива Iraníes por $ 40 millones se hunde plataforma petrolera a fondo del Golfo Pérsico
https://wn.com/Iranian_40_Million_Oil_Platform_Sinks_To_Bottom_Of_Persian_Gulf
Allseas Pioneering Spirit removing Brent Delta topsides 1080p

Allseas Pioneering Spirit removing Brent Delta topsides 1080p

  • Order:
  • Duration: 2:37
  • Updated: 29 Apr 2017
  • views: 56820
videos
Allseas' "Pioneering Spirit" removes the 24,000 Tons Brent D Topsides for Shell UK in the North Sea
https://wn.com/Allseas_Pioneering_Spirit_Removing_Brent_Delta_Topsides_1080P
Gina Krog topside installation August 2016

Gina Krog topside installation August 2016

  • Order:
  • Duration: 1:00
  • Updated: 28 Aug 2016
  • views: 5539
videos
In less than a week all the modules for the Gina Krog topside was installed at the field in the North Sea in August 2016 by Saipem 7000. The complete weight of the topside is close to 20 000 tonne. The main support frame, process module and utility module was constructed by DSME at Okpo, South Korea, the living quarter was constructed by Apply Leirvik at Stord, Norway. The Gina Krog platform will come on stream in 2017.
https://wn.com/Gina_Krog_Topside_Installation_August_2016
Anadarko: Lucius Topsides Installation

Anadarko: Lucius Topsides Installation

  • Order:
  • Duration: 2:47
  • Updated: 10 Jun 2014
  • views: 9969
videos
Hundreds of people worked around the clock to successfully install the 10,000-ton topsides on Anadarko's floating Lucius truss spar. This massive structure is located nearly 275 miles southeast of Galveston, Texas in approximately 5,300 feet of water in the Gulf of Mexico. The successful setting of the topsides brought together a tapestry of components built in Orange, Texas; Houma, La; and Ingleside, Texas, among other locations worldwide. Lucius is Anadarko's largest spar to date with a nameplate capacity of 80,000 barrels of oil per day.
https://wn.com/Anadarko_Lucius_Topsides_Installation
Offshore Platform Construction Topside Module Installation

Offshore Platform Construction Topside Module Installation

  • Order:
  • Duration: 5:31
  • Updated: 13 Jul 2017
  • views: 0
videos
Offshore Platform Construction Topside Module Installation
https://wn.com/Offshore_Platform_Construction_Topside_Module_Installation
Offshore Platform Construction  Topside Module Installation

Offshore Platform Construction Topside Module Installation

  • Order:
  • Duration: 5:31
  • Updated: 12 May 2017
  • views: 8
videos
https://wn.com/Offshore_Platform_Construction_Topside_Module_Installation
Single Lift Vessel Platform Removal

Single Lift Vessel Platform Removal

  • Order:
  • Duration: 9:37
  • Updated: 14 Aug 2017
  • views: 9
videos
SLCV demonstration movie showing the removal of a platform topsides in a single lift.
https://wn.com/Single_Lift_Vessel_Platform_Removal
Offshore Platform Construction  Topside Module Installation

Offshore Platform Construction Topside Module Installation

  • Order:
  • Duration: 5:31
  • Updated: 28 Aug 2014
  • views: 16
videos
https://wn.com/Offshore_Platform_Construction_Topside_Module_Installation
Offshore Platform Construction- Topside Module Installation HOT MOBILE LOCATION

Offshore Platform Construction- Topside Module Installation HOT MOBILE LOCATION

  • Order:
  • Duration: 5:31
  • Updated: 14 May 2017
  • views: 2
videos
https://wn.com/Offshore_Platform_Construction_Topside_Module_Installation_Hot_Mobile_Location
×